Chelan County
PUD
Rocky
Reach Project
Plant
size - 1347 MW
Flow
measurements on four units at Rocky Reach in January, 1992, were the first
commercial use of a prototype ASFM. The ASFM was selected by Chelan's
personnel because the previously used arrays of current meters were time-consuming,
costly and subject to flow interference from the support frame. The ASFM
flow measurements were obtained rapidly and accurately and the results
were used by the client as input into a downstream migrant fish bypass
project. Back
Chelan
County's own Rocky Reach Web-Page

Rock
Island Hydro Project
Plant
size - 668 MW
Publication: presented at Waterpower
XII 2001
(PDF format - 551kb)
In
August 2000, as part of a plant optimization program, Chelan County PUD
required index tests and absolute flow measurements at selected turbines.
As several of these were bulb units with very short and rapidly converging
intakes, the ASFM was chosen because of its ability to measure flow using
unobtrusive acoustic paths oriented directly across the intake. The results
confirmed that the ASFM will deliver accurate, absolute discharge measurements
under these difficult hydraulic conditions. Back
Chelan
County's own Rock Island Web-Page

| Brookfield Renewable Power |
Dolby - 2008
|
New York Power Authority |
St. Lawrence-FDR – 2007, 2008
|
Union Fenosa
Generación |
Velle - 2007
|
Frieira - 2007
|
Castrelo - 2007
|
| Electricité de France |
Pinet - 2007
|
Cusset - 2007
|
La Rance - 2007
|
Sisteron - 2007
|
Kembs - 2006
|
| Douglas County PUD |
Wells - 2002,2004,2005,2006,2007, 2008
|
| Korea Water Resources Corp. |
Namgang - 2006
|
Yongdam - 2005
|
| Hydro Québec |
Rocher-de-Grand-Mère - 2006
|
La Grande 1 - 2003
|
Outardes II - 2002
|
Rapides des Quinze - 2002
|
Coteau Rapids Spillway - 2000
|
Les Cèdres - 2000
|
Laforge-2 - 1997
|
| Portland General Electric |
TW Sullivan - 2005
|
| Edison Sault Electric Company |
2004
|
| US Army Corps of Engineers |
Chief Joseph - 2008
|
Lower Granite - 1995, 2004
|
Little Goose - 2003
|
Lower Monumental - 2002
|
John Day - 2001
|
The Dalles - 2000, 2001
|
Bonneville - 1998, 1999, 2000
|
McNary - 1998, 1999
|
| Hydro Kennebec |
2003
|
| Nova Scotia Power |
Hells Gate - 2002
|
Deep Brook - 2001
|
| BC Hydro |
Stave Falls - 2000
|
Revelstoke - 1996
|
| Chelan County PUD |
Rocky Reach - 1992, 1993, 2000
|
Rock Island- 2000
|
| Swed Power, Sweden |
Mellanfallet spillway - 1999
|
| Manitoba Hydro |
Seven Sisters - 1999
|
| Tennessee Valley Authority |
Wheeler - 1999
|
Fort Patrick Henry - 1997
|
|